About the project
Construction started Sept. 2026 on a former Raytheon site; 102 of 341 units are workforce or affordable. Timing per St. Pete Catalyst groundbreaking report (https://stpetecatalyst.com/ground-broken-for-azalea-cay-multi-family-community/).
Site facts
- Flood zone (FEMA)
- X · outside the high-risk flood area
- Zoning
- IS · INDUSTRIAL SUBURBAN
At the mapped point, not a survey. Check the official map before relying on it.
The parties
- Developer / owner
- Metro Development Group, Porter Development
Details
- Stage
- Under construction
- Property type
- Multifamily
- Delivery
- About 24 months after the Sept. 2026 start
- Homes
- 341
- Address
- 1501 72nd St N
- Area
- Azalea, St. Petersburg, Pinellas County
Status history
- Under construction · Sep 29, 2026