EDGE Collective II
1100 Central Ave · EDGE District · St. Petersburg · Pinellas
330units
20stories
2028delivery
About the project
Sitework started Aug. 2026 at 11th St. S and 1st Ave. S; $125M construction loan closed Oct. 2026; 17,000-19,000 SF retail. Address from St. Pete Rising project page; late-2028 completion target from Florida YIMBY (Aug. 2026).
Site facts
- Flood zone (FEMA)
- X · outside the high-risk flood area
- Zoning
- DC-1 · DOWNTOWN CENTER
At the mapped point, not a survey. Check the official map before relying on it.
The parties
- Developer / owner
- PTM Partners
Details
- Stage
- Under construction
- Property type
- Mixed-use
- Delivery
- Late 2028
- Homes
- 330
- Stories
- 20
- Address
- 1100 Central Ave
- Area
- EDGE District, St. Petersburg, Pinellas County
Status history
- Under construction · Aug 16, 2026
- Approved · Oct 5, 2026